Bathroom renovation step by step

From strip-out to the final wet-room inspection — what happens each week and what you need to decide when.

A normal bathroom takes three to five weeks. The schedule is driven by drying times and inspection, not by how fast we can work.

Week 1 — strip-out and pipework

Every old surface comes off down to the structural substrate. If the pipes are old, this is when they are replaced, while the walls are open anyway.

Weeks 2–3 — waterproofing and drying

The floor is laid to fall towards the drain, the waterproof membrane is rolled on in two coats, and it must dry before tiling starts. It cannot be rushed.

Weeks 4–5 — tiling and fit-out

Wall and floor tiles go on, then grouting and silicone. Sanitaryware, taps and electrics are fitted last.

We always issue a wet-room certificate. Without it your insurance will not cover a water escape.

Choose your tiles and sanitaryware before the strip-out begins. Lead times on what you pick are the most common reason a bathroom overruns.